A restaurant on South Fraser Way in Abbotsford: single storey over a basement, wood frame behind metal siding and brick, built in 1976. In the winter of 2022 it was gutted and rebuilt inside — lobby, dining room, washrooms, the basement staff room, and alterations in the kitchen. Six weeks, start to finish.

It did not close. The drive-thru served customers the whole way through.

That combination — a live business, a building site inside it, and a six-week clock — is why the construction fire safety plan for this job is more interesting than the building is.

The alarm went on bypass

Here is the line that shapes everything else. From the plan:

The entire building is equipped with a fire alarm system. The panel will be placed on bypass during the construction.

That is normal and it is necessary. Drilling, cutting and dust will put an active system into alarm repeatedly, and a system that cries wolf during a renovation gets ignored or silenced, which is worse than having it off deliberately.

Notifier fire alarm control panel in an Abbotsford restaurant, the panel placed on bypass during renovation
The panel that went on bypass. For six weeks it was not watching anything — a person was.

But it means that for six weeks the building had no automatic detection and no automatic notification — while still serving the public through the drive-thru.

What replaces it is a fire watch: a named person, patrolling, whose job is to find a fire the way a detector would have. The plan is explicit that the watch covers the entire building, not just the area under construction, because the fire does not know where the hoarding is. There is a log, and the log is the evidence that the watch happened.

This building also had no sprinkler system, which removes the other automatic layer. Detection was a person. Suppression was extinguishers and the fire department.

Hot work, planned for even though none was planned

The contractor advised there would be no hot work — no welding, cutting or grinding.

The plan carries the full hot work regime anyway: a permit system, a fifteen-metre clear radius, a fire watch during the work and for sixty minutes after, a final inspection of the area four hours later, extinguishers staged at specified ratings, and trained personnel only.

That is deliberate. “No hot work planned” is a statement about intentions at the start of a job. Somewhere in week four a subcontractor needs to cut one bracket, and the question becomes whether there is a procedure or an improvisation. Writing the regime into the plan up front means the answer is already decided.

The construction plan is not the occupancy plan

This is the part owners most often get wrong, and this building shows both halves of it.

A construction fire safety plan is written under Section 5.6 of the BC Fire Code. It governs a site: the contractor’s Fire Safety Director, instructions to construction staff, the fire watch log, hot work permits, a weekly checklist, the scope of work and its dates, and how fire department access is kept clear past the trades’ vehicles.

An occupancy fire safety plan is written under Section 2.8. It governs a building in use: the owner’s Fire Safety Director, occupant procedures, the inspection and testing schedule for every installed system, drills, and what staff do when the alarm sounds.

They share a cover format and almost nothing else. The construction plan expires when the work does, and the occupancy plan has to exist before anyone is served inside the finished room. We wrote both for this building, and then revised the occupancy plan again the following year when things changed.

Manual pull station for the kitchen fire suppression system on a stainless hood in an Abbotsford restaurant
The manual release for the kitchen suppression system — part of the occupancy plan, not the construction one.

If you are renovating an occupied building, you need the construction plan on day one and the occupancy plan — new or updated — before you reopen the affected area. Discovering that in week five is the expensive way to find out.

What Abbotsford wanted to see

Abbotsford Fire Rescue Service reviewed the plan for the renovation and the occupancy plan that followed. The construction submission had to show the scope and the dates, who the construction Fire Safety Director and deputy were, how the fire watch would run while the panel was bypassed, the hot work procedure, where hydrants sat relative to the site, and that fire department access would not be blocked by the work.

The site drawings also had to show what stays open. When part of a building keeps trading, the exits serving the public and the exits serving the trades are not the same set, and the plan has to say which is which.

If you are renovating an occupied building

The questions worth settling before the first day. Is the fire alarm going on bypass, and for how long? Who is the fire watch, how often do they patrol, and where is the log? Does the watch cover the whole building or only the work area? Is the building sprinklered — and if not, do you understand what you are left with? Is there a hot work procedure written down before somebody needs it? And is your occupancy plan ready for the day you reopen, or does it still describe the room you just demolished?

We write the construction plan and the occupancy plan that replaces it, draw both to scale, and submit through to acceptance. Tell us about the project and we will quote it, usually the same day. Construction-phase plans are handled by our construction fire safety plan division.

Also in Abbotsford

Need a fire safety plan in Abbotsford?

GetFirePlan prepares CAD-designed fire safety plans accepted by the fire department, with one flat fee and an approval guarantee.

More from Abbotsford

Related guides

Also visit our sister site: FireSafetyPlan.com — Fire Safety Plans for strata and commercial buildings across BC. Building or renovating? See Construction Fire Safety Plans for BC job sites.